Due Date-Based Metrics for Activity Importance in Stochastic Activity Networks
Authors:R.A. Bowman
Affiliation:(1) Graduate Management Institute, Union College, Lamont Graduate Center, 1 Union Avenue, Schenectady, NY 12308, USA
Abstract:A metric pair for assessing the importance of activities in stochastic activity networks based on completing a project on time (or reaching other project milestones) is presented. The metric pair is recommended as a supplement to other metrics of activity importance that have been suggested for use with Monte Carlo simulation. The differences in behavior of the various metrics are analyzed to help understand the additional types of insights that would be available by including the new metrics in simulation-based analyses.
Keywords:PERT  project management  stochastic activity networks  activity criticality  conditional estimators  Monte Carlo simulation