六西格玛管理中的网络计划技术及其应用
引用本文:陶靖轩. 六西格玛管理中的网络计划技术及其应用[J]. 数学的实践与认识, 2007, 37(1): 43-48
作者姓名:陶靖轩
作者单位:中国计量学院管理科学分院,杭州,310018
基金项目:国家质量监督检验检疫总局科研项目
摘    要:利用网络计划技术,对节点(事项)和箭条(作业活动)分别规定了六个时间值,讨论了他们之间的关系;结合实例应用,分析了资源的合理配置,得到了有一定参考意义的结果.

关 键 词:网络计划  关键路线  资源优化  质量改进  总时间差
修稿时间:2004-10-11

Network-based Planning Techniques and Its Application
TAO Jing-xuan. Network-based Planning Techniques and Its Application[J]. Mathematics in Practice and Theory, 2007, 37(1): 43-48
Authors:TAO Jing-xuan
Abstract:This article which utilizes the network-based planning techniques,has stipulated six time values to the node(item) and arrow strip(work activity) respectively and discussed the relations between them.Furthermore,a certain result that covers some referenced significance has been acquired by combining instance application and analyzing the reasonable disposition of resources.
Keywords:network-based plan  key route  resource optimization  quality improvement  total time difference  