HL-2M 装置主机集成安装工程质量管理
引用本文:蔡立君,宋斌斌,李连才,徐红兵,杨 泓,林 晨,毛维成,HL-M 研制团队.HL-2M 装置主机集成安装工程质量管理[J].核聚变与等离子体物理,2021,41(Z1):289-294.
作者姓名:蔡立君  宋斌斌  李连才  徐红兵  杨 泓  林 晨  毛维成  HL-M 研制团队
作者单位:(核工业西南物理研究院,成都 610041)
摘    要:基于 HL-2M 装置主机集成安装实践,以风险控制、过程管理为质量管理工作总体思路,对工程策 划、实施、验收环节进行全面质量管理。通过实施质量管理活动,确保了 HL-2M 装置主机集成安装工程达到质 量目标,并于 2020 年 12 月 4 日首次放电成功。通过本项目的实施积累了大科学工程的质量管理经验。

关 键 词:HL-2M  装置  主机安装  质量管理   
收稿时间:2021-04-15

Quality management of HL-2M tokamak assembly and installation
CAI Li-jun,SONG Bin-bin,LI Lian-cai,XU Hong-bin,YANG Hong,LIN Chen,MAO Wei-cheng,HL-M Development Team.Quality management of HL-2M tokamak assembly and installation[J].Nuclear Fusion and Plasma Physics,2021,41(Z1):289-294.
Authors:CAI Li-jun  SONG Bin-bin  LI Lian-cai  XU Hong-bin  YANG Hong  LIN Chen  MAO Wei-cheng  HL-M Development Team
Institution:(Southwestern Institute of Physics, Chengdu 610041)   
Abstract:The main components of HL-2M tokamak have the characteristics of large scale, complex  structure, compact internal space, and complex integrated assembly process and high assembly precision  requirements. The assembly and installation of the main components are the final key process in the development  and construction of the main components of HL-2M tokamak, which has a direct impact on the project quality and  the total construction period. Based on the practice of HL-2M tokamak assembly and installation, taking risk  control and process management as the general idea of quality management, quality management was carried out  from the aspects of project planning, implementation and acceptance to effectively ensure the smooth  implementation of the project. Through the implementation of quality management activities, the quality  objectives for the HL-2M tokamak assembly and installation project were achieved, and HL-2M tokamak passed  the acceptance of the expert group and the quality management experience of large scale scientific engineering  project was accumulated. The HL-2M first discharge was successful on December 4, 2020. 
Keywords:HL-2M tokamak  Assembly and installation  Quality management  