Functional estimation of activity criticality indices and sensitivity analysis of expected project completion time |
| |
Authors: | J-G Cho B-J Yum |
| |
Institution: | 1.Dong-Eui University,Busan,Korea;2.Korea Advanced Institute of Science and Technology,Taejon,Korea |
| |
Abstract: | For a PERT network, a new method is developed for estimating the criticality index of activity i (ACI i ) as a function of the expected duration of activity i (μ i ) and for the sensitivity analysis of the expected project completion time (μ T ) with respect to μ i . The proposed method evaluates the frequency of activity i being on the critical path, and thereby its ACI i using Monte Carlo simulation or a Taguchi orthogonal array experiment at several values of μ i , fits a logistic regression model for estimating ACI i as a function of μ i , and then, using the estimated ACI i function, evaluates the amount of change in μ T when μ i is changed by a given amount. Unlike the previous works, the proposed method models ACI i as a nonlinear (ie, logistic) function of μ i , which can be used to estimate the amount of change in μ T for a variety of changes in μ i . Computational results indicate that the performance of the proposed method is comparable to that of direct Monte Carlo simulation. |
| |
Keywords: | |
本文献已被 SpringerLink 等数据库收录! |
|