Properties of multi-mode resource-constrained project scheduling problems with resource vacations and activity splitting
Institution:1. Université de Technologie de Compiègne, Heudiasyc, CNRS UMR 7253 Rue Roger Couttolenc, Compiègne, CS 60319, 60203 France;2. LIMOS CNRS UMR 6158, LABEX IMOBS3, Université Blaise Pascal Bat. ISIMA, BP 10125, Campus des Cézaux, Aubière, 63173 France;3. LIMOS CNRS UMR 6158, LABEX IMOBS3, CNRS Bat. ISIMA, BP 10125, Campus des Cézaux, Aubière, 63173 France
Abstract:This paper presents results from an extensive computational study of the multi-mode resource-constrained project scheduling problem when activities can be split during scheduling under situations where resources may be temporarily not available. All resources considered are renewable and each resource unit may not be available at all times due to resource vacations, which are known in advance, and assignment to other finite duration activities. A designed experiment is conducted that investigates project makespan improvement when activity splitting is permitted in various project scenarios, where different project scenarios are defined by parameters that have been used in the research literature. A branch-and-bound procedure is applied to solve a number of small project scheduling problems with and without activity splitting. The results show that, in the presence of resource vacations and temporary resource unavailability, activity splitting can significantly improve the optimal project makespan in many scenarios, and that the makespan improvement is primarily dependent on those parameters that impact resource utilization.
Keywords:
本文献已被 ScienceDirect 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号