A robust decomposition method for the analysis of production lines with unreliable machines and finite buffers
Authors:Hervé Le Bihan  Yves Dallery
Institution:(1) Laboratoire d'Informatique de Paris 6, Université Pierre et Marie Curie, 4 Place Jussieu, Fdash75252 Paris cedex 05, France;(2) Laboratoire ProductiquedashLogistique, Ecole Centrale de Paris, Grande Voie des Vignes, Fdash92295 ChatenaydashMalabry cedex, France
Abstract:We consider production lines consisting of a series of machines separated by finite buffers. The processing time of each machine is deterministic and all the machines have the same processing time. All machines are subject to failures. As is usually the case for production systems we assume that the failures are operation dependent 3,7]. Moreover, we assume that the times to failure and the repair times are exponentially distributed. To analyze such systems, a decomposition method was proposed by Gershwin 13]. The computational efficiency of this method was later significantly improved by the introduction of the sodashcalled DDX algorithm 5,6]. In general, this method provides fairly accurate results. There are, however, cases for which the accuracy of this decomposition method may not be acceptable. This is the case when the reliability parameters (average failure time and average repair time) of the different machines have different orders of magnitude. Such a situation may be encountered in real production lines. In 8], an improvement of Gershwin's original decomposition method has been proposed that in general provides more accurate results in the above mentioned situation. This other method is referred to as the Generalized Exponential (GE) method. The basic difference between the GEdashmethod and that of Gershwin is that it uses a twodashmoment approximation instead of a singledashmoment approximation of the repair time distributions of the equivalent machines. There are, however, still cases for which the accuracy of the GEdashmethod is not as good as expected. This is the case, for example, when the buffer sizes are too small in comparison with the average repair time. We present in this paper a new decomposition method that is based on a better approximation of the repair time distributions. This method uses a threedashmoment approximation of the repair time distributions of the equivalent machines. Numerical results show that the new method is very robust in the sense that it seems to provide accurate results in all situations.
Keywords:production lines  unreliable machines  finite buffers  decomposition method  hyperdashexponential distributions" target="_blank">gif" alt="dash" align="MIDDLE" BORDER="0">exponential distributions
本文献已被 SpringerLink 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号