大坂山隧道病害处治工程工艺设计与实证分析
引用本文:刘海京,郑佳艳,程崇国,黄伦海.大坂山隧道病害处治工程工艺设计与实证分析[J].重庆大学学报(自然科学版),2011,34(12):138-143.
作者姓名:刘海京  郑佳艳  程崇国  黄伦海
作者单位:重庆交通科研设计院 交通部隧道建设与养护行业重点实验室,重庆 400067;重庆交通大学 土木建筑学院,重庆 400074;重庆交通科研设计院 交通部隧道建设与养护行业重点实验室,重庆 400067;重庆交通科研设计院 交通部隧道建设与养护行业重点实验室,重庆 400067
基金项目:交通部应用基础研究项目(2007319740120);重庆市科技攻关项目(CSPC,2009AC6083)
摘    要:在国道227线控制工程大坂山隧道病害检测基础上,综合考虑高寒隧道工程地质、水文、气候等自然特征和原隧道施工工艺、施工工法、运营养护等人为因素,分析了渗漏水、衬砌裂缝、低温冻融、混凝土材料劣化等病害演化过程,以及各种不良因素在高寒隧道病害演化发展过程中所起的作用。在病害成因分析的基础上,介绍了大坂山高寒隧道渗漏水、保温、衬砌加固等病害处治的基本原则、思路和具体措施,为后续类似高寒隧道和寒区隧道的病害处治提供经验和借鉴。

关 键 词:大坂山隧道  高寒隧道  病害处治

Rehabilitation project of the Dabanshan highland road tunnel
LIU Hai jing,ZHENG Jia yan,CHENG Chong guo and HUANG Lun hai.Rehabilitation project of the Dabanshan highland road tunnel[J].Journal of Chongqing University(Natural Science Edition),2011,34(12):138-143.
Authors:LIU Hai jing  ZHENG Jia yan  CHENG Chong guo and HUANG Lun hai
Institution:Key Laboratory of Road tunnel Construction and Maintenance of the Communication Ministry,Chongqing Communications Research and Design Institute, Chongqing 400067,P.R. China;Chongqing Jiaotong University,Chongqing 400074, P.R. China;Key Laboratory of Road tunnel Construction and Maintenance of the Communication Ministry,Chongqing Communications Research and Design Institute, Chongqing 400067,P.R. China;Key Laboratory of Road tunnel Construction and Maintenance of the Communication Ministry,Chongqing Communications Research and Design Institute, Chongqing 400067,P.R. China
Abstract:The rehabilitation project of road tunnel in highland area and cold region is an important and worthy exploring research field. The development of the defects of crack in the liner, water leakage, structural deterioration and frost defects for Dabanshan road tunnel are studied. After an insight into the cause and development of tunnel defects, the water leakage and frost damage are considered as the root of defect, so restoration of drainage system and the reinstallation of cold prevention system are the focuses of the rehabilitation project. For consideration of safety, cover arch is installed for the tunnel structure enforcement as well. Results indicate measures in Dabanshan road tunnel rehabilitation project are effective for road tunnel of high altitude and tunnel in cold region.
Keywords:road tunnel of high altitude  tunnel liner defects  tunnel repair and rehabilitation