时序控制预裂爆破参数优化及应用
引用本文:叶海旺,唐可,万涛,王超,雷涛,李新平,C.M.Saliou.时序控制预裂爆破参数优化及应用[J].爆炸与冲击,2017,37(3):502-509.
作者姓名:叶海旺  唐可  万涛  王超  雷涛  李新平  C.M.Saliou
作者单位:武汉理工大学资源与环境工程学院,湖北武汉430070;武汉理工大学矿物资源加工与环境湖北省重点实验室,湖北武汉430070;武汉理工大学资源与环境工程学院,湖北武汉,430070;武汉理工大学土木与建筑工程学院,湖北武汉,430070
基金项目:国家自然科学基金项目,中央高校基本科研业务费专项基金项目
摘    要:针对白鹤滩水电站地下厂房的爆破开挖,为降低爆破对岩体的损伤,采用数值模拟与现场试验研究小孔径时序控制预裂爆破中,后爆孔孔间延期时间及后爆孔孔距对时序控制预裂爆破成缝的影响,从而获取合理的延期时间和最佳的后爆孔孔距。研究结果表明,孔径为42mm的时序控制预裂爆破,先爆孔孔距为35cm时,合理的起爆延期时间为75~100μs;综合考虑炸药爆炸能量利用率和成缝效果,最佳的后爆孔孔距为70cm。科学地采用时序控制预裂爆破不仅可以减小钻孔工作量与炸药用量,还能降低对岩体的损伤,可为地下厂房爆破开挖安全、高效的进行提供一条有效的途径。

关 键 词:时序控制预裂爆破  起爆延期时间  后爆孔孔距  现场试验
收稿时间:2015-11-09

Optimization of time sequence controlled pre-splitting blasting parameters and its application
Ye Haiwang,Tang Ke,Wan Tao,Wang Chao,Lei Tao,Li Xinping,C.M.Saliou.Optimization of time sequence controlled pre-splitting blasting parameters and its application[J].Explosion and Shock Waves,2017,37(3):502-509.
Authors:Ye Haiwang  Tang Ke  Wan Tao  Wang Chao  Lei Tao  Li Xinping  CMSaliou
Institution:1.School of Resources and Environmental Engineering, Wuhan University of Technology, Wuhan 430070, Hubei, China2.Hubei Key Laboratory of Mineral Resources Processing and Environment, Wuhan University of Technology, Wuhan 430070, Hubei, China3.School of Civil Engineering and Architecture, Wuhan University of Technology, Wuhan 430070, Hubei, China
Abstract:In view of the underground powerhouse excavation work by blasting at the Baihetan Hydropower Station Project,in order to reduce the blasting-involved damage to the rock mass,numerical simulation and field test were carried out to analyze the influence of the initiation delay time and the distance between later detonated holes on the blasting and the cracking with time sequence controlled pre-splitting blasting,and the reasonable delay time and the optimum distance between post-detonated holes were obtained.The results show that when the hole diameter is 42 mm and the distance between the pre-detonated holes is 35 cm,the reasonable initiation delay time is 75~100 μs,and the optimum distance between the post-detonated holes is 70cm,with joint consideration of the blasting energy's utilization ratio and blasting effect.It is found that time sequence controlled pre-splitting blasting,used scientifically,is a safe and efficient method to excavate the rock mass close to the underground powerhouse wall,which can reduce the load of blasting,cut down on the explosives used,and limit the blasting-involved damage to rock mass.
Keywords:time sequence controlled pre-splitting blasting  initiation delay time  distance between later detonated holes  field test