Scheduling jobs with different,job-dependent earliness and tardiness penalties using the SLK method
Authors:GI Adamopoulos  CP Pappis
Institution:Department Industrial Management, University of Piraeus, 80 Karaoli & Dimitriou str., 185 34 Piraeus, Greece
Abstract:The single machine job scheduling problem, where due dates are assigned using the SLK due date determination method, is examined assuming different penalties for the early and tardy jobs. These penalties are assumed to be job-dependent, proportional to the processing times of jobs raised to an integer, non-negative power. The objective function is the total weighted lateness. Several cases are examined and four algorithms providing the optimal sequences for these cases are presented. Examples are given and conclusions are drawn.
Keywords:Due date  Weighted lateness  Slack time  Scheduling