Minimizing total weighted late work in the resource-constrained project scheduling problem
Authors:Mohammad Ranjbar  Saeed Hosseinabadi  Foroogh Abasian
Institution:Department of Industrial Engineering, Faculty of Engineering, Ferdowsi University of Mashhad, Mashhad, P.O. Box 91775-1111, Iran
Abstract:This paper deals with resource-constrained project scheduling problem under the weighted late work criterion. Late work objective functions estimate the quality of a schedule based on durations of late parts of activities, not taking into account the amount of delay for fully late activities. It is assume that a project contains activities interrelated by finish-to-start type precedence relations with time lag of zero, which require one or more constrained renewable resources. The objective is to schedule each activity such that the total weighted late work is minimized. The problem has been formulated using a linear integer programming model and solved by the CPLEX. Also, a set of priority rules have been designed to quickly generate a set of initial solutions. In order to solve the problem optimally, a depth-first branch-and-bound algorithm is applied based on idea of minimal delaying alternatives. The branching order of nodes that belong to the same level of the search tree is determined on the basis of the developed priority rules. This results in generation six different versions of the branch-and-bound algorithm. Computational results on randomly generated problem sets are provided to analyze the efficiency of the priority rules and the branch-and-bound algorithm.
Keywords:Resource-constrained project scheduling  Late work  Branch-and-bound
本文献已被 ScienceDirect 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号