Scheduling project networks with resource constraints and time windows
Authors:M. Bartusch  R. H. Möhring  F. J. Radermacher
Affiliation:(1) Lehrstuhl für Informatik und Operations Research, Universität Passau, W.-Germany;(2) Fachbereich Mathematik, TU Berlin W.-Germany, Universität Bonn, supported by Sonderforschungsbereich 303 (DFG), Germany;(3) Forschungsinstitut für Anwendungsorientierte Wissensverarbeitung, Ulm, W.-Germany
Abstract:
Project networks with time windows are generalizations of the well-known CPM and MPM networks that allow for the introduction of arbitrary minimal and maximal time lags between the starting and completion times of any pair of activities.We consider the problem to schedule such networks subject to arbitrary (even time dependent) resource constraints in order to minimize an arbitrary regular performance measure (i.e. a non-decreasing function of the vector of completion times). This problem arises in many standard industrial construction or production processes and is therefore particularly suited as a background model in general purpose decision support systems.The treatment is done by a structural approach that involves a generalization of both the disjunctive graph method in job shop scheduling [1] and the order theoretic methods for precedence constrained scheduling [18,23,24]. Besides theoretical insights into the problem structure, this approach also leads to rather powerful branch-and-bound algorithms. Computational experience with this algorithm is reported.
Keywords:Scheduling  project networks  MPM-networks  time-windows  order theoretic approach to scheduling  disjunctive graph method
本文献已被 SpringerLink 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号