Project Management Duration/Resource Tradeoff Analysis: an Application of the Cut Search Approach |
| |
Authors: | Jr" target="_blank">Steve PhillipsJr |
| |
Institution: | 1.George College, University System of Georgia, |
| |
Abstract: | The paper presents an application oriented procedure for solving the project management duration/resource tradeoff problem. A procedure is presented for reducing a project from a normal to a crash duration state at a minimum amount of additional resource expenditure assuming a linear utilization functions. The procedure is network based using a graphical Cut Search Approach to locate the minimal resource level at each reduction in total project duration. Activity-on-arc networks and flow networks are utilized. The paper is presented for practical application and for conceptual development as compared to a theoretical treatment. |
| |
Keywords: | |