交叉隧道塑性区分布规律、成因及支护探讨
引用本文:范永波,伍法权,胡社荣,吴查查,任爱武.交叉隧道塑性区分布规律、成因及支护探讨[J].力学学报,2008,16(2):268-272.
作者姓名:范永波  伍法权  胡社荣  吴查查  任爱武
作者单位:中国科学院地质与地球物理研究所工程地质力学重点实验室 北京 100029; 中国矿业大学(北京) 北京 100083; 北京市国土资源遥感公司 北京 100085
基金项目:中国青年科学基金项目(40302032).
摘    要:在既有隧道区间上方近距离进行新车站的施工,是地下工程研究中难度较大的问题。本文运用数值模拟方法对北京市地铁五号线东单站上跨地铁一号线,采用浅埋暗挖法施工过程中隧道塑性区分布问题进行了研究,得出在杂填土、砂土、粘土互层条件下大跨度车站底板受既有线存在的影响其塑性区基本以车站轴线为对称轴的矩形分布、既有隧道区间塑性区不同部位的变化幅度,其中以两侧壁最大,并进行了锚杆支护模拟,保证了土体的稳定。

关 键 词:塑性区  锚索  FLAC  既有隧道区间  地铁车站
收稿时间:2007-03-06
修稿时间:2007-10-15

DISTRIBUTION OF PLASTIC ZONES IN EXISTING TUNNEL DUE TO NEW CONSTRUCTION CLOSELY ABOVE THE TUNNEL AND THEIR MECHANISM AND REINFORCEMENT, A CASE STUDY IN BEIJING
FAN Yongbo,WU Faquan,HU Sherong,WU Chacha,REN Aiwu.DISTRIBUTION OF PLASTIC ZONES IN EXISTING TUNNEL DUE TO NEW CONSTRUCTION CLOSELY ABOVE THE TUNNEL AND THEIR MECHANISM AND REINFORCEMENT, A CASE STUDY IN BEIJING[J].chinese journal of theoretical and applied mechanics,2008,16(2):268-272.
Authors:FAN Yongbo  WU Faquan  HU Sherong  WU Chacha  REN Aiwu
Institution:Key Laboratory of Engineering Geo mechanics, Institute of Geology and Geophysics, Chinese Academy of Sciences, Beijing 100029; China University of Mining &|Technology, Beijing 100083; Beijing Remote Sensing Corporation, Beijing 100085
Abstract:Building a new station closely above an existing tunnel is a relatively difficult problem in underground construction. This paper uses numerical simulation methods and analyzes the distribution of plastic zones in the tunnel of the No. 1 Subway Line during the above construction of the Dongdan station for the No. 5 Subway Line in Beijing. It found that the symmetrical andrectangular distribution of plastic zones for the large-span station floor s influenced by existing line. Changing extent of different parts were also found on the plastic zones of the existing tunnel under backfill, sandy soil, clay interbedding,. The plastic zone valuesabout the side face of the existing line are the largest. Simulation on the reinforcement scheme was also conducted to guarantee the stabilization of the surrounding ground.
Keywords:Plastic zone  Numerical analysis  Tunnel engineering  Metro-station
点击此处可从《力学学报》浏览原始摘要信息
点击此处可从《力学学报》下载免费的PDF全文
设为首页 | 免责声明 | 关于勤云 | 加入收藏